Proposed Rule Amendments: §§ 3.15 and 3.58

The proposed amendments to rules §§ 3.15 and 3.58, related to Senate Bill 1150 (89th Legislative Session, 2025), have been posted for public comment. Comments will be accepted until 5:00 pm on Friday, November 13, 2026. For more information, including an online comment form, please visit the RRC Proposed Rules page.

Scheduling of Mechanical Integrity Tests

Quarterly test schedules.

  • At the beginning of each calendar quarter, a computer program searches the RRC data system for wells that are due for a mechanical integrity test.
  • Computer-generated testing schedule is then sent to the operator of each of these wells.
  • Any successful pressure test effectively "resets the clock."

Types of tests scheduled.

  • Initial pressure tests on wells with new or newly amended permits.
  • Five-year pressure tests.
  • Annual pressure tests required by permit.

Time allowed to perform tests.

  • Initial test - 3 months.
  • Five-year test - months.
  • Annual test - months.