Notice to Operators: RRC Online Payments will be intermittently unavailable November 22, 2026, from 10:00 PM to 10:30 PM CT.  During this time, customers using RRC applications will be unable to process online payments through Texas.gov payment services and will be redirected to a maintenance page and unable to complete payments until after the maintenance is complete.  

Proposed Rule Amendments: §§ 3.15 and 3.58

The proposed amendments to rules §§ 3.15 and 3.58, related to Senate Bill 1150 (89th Legislative Session, 2025), have been posted for public comment. For more information, including an online comment form, please visit the RRC Proposed Rules page.

The RRC will host a hybrid public hearing to receive verbal comments, beginning at 10 a.m., on Friday, November 20, 2026. For more information, please visit the RRC's Public hearing announcement.

Non-Compliance/Enforcement Action

Failed Tests

  • Shut in well immediately.
  • Notify the district office within 24 hours - as specified in Rule 9 (11)(D), and 46 (i)(4).
  • Submit test results on Form H-5 within 30 days. Note that filing the pressure test report is required on all pressure tests, whether passed, failed, or inconclusive.
  • The Commission will typically require that the well be repaired and retested within 60 days.

Delinquent Tests

  • 60 days past the due date, the Commission sends the operator a second notice of the need to file Form H-5.
  • Enforcement action is initiated 30 days after the second notice if the operator has not contacted Technical Permitting regarding compliance.
    • Well sealed in if no production exists on the lease.
    • Lease pipeline connection severed if production exists.

Compliance

A well becomes compliant with the scheduled test requirement when the pressure test report (Form H-5) is received in the District Office. This date is important if the lease is severed/sealed-in for non-compliance. The pipeline reconnection fee must be paid if the well was non-compliant on the date of the severance.



Commissioners